Acumatica migrations: EVA progress report

Weekly progress report · Earned Value Analysis

Week 2 of 142 – 8 Nov 2026On schedule · Under budget

Performance metrics

SPI · Schedule performance
1.00
= EV / PV
On schedule
CPI · Cost performance
1.30
= EV / AC
Under budget
EAC · Estimate at completion
507 h
= BAC / CPI = 659 / 1.30
≈152 h under budget

Progress by milestone

MilestoneProgressStatus
1Foundation and Acumatica connectivity
100%Complete
2Customers
45%In progress
3Invoices
20%In progress
4Payments
0%Not started
5Refunds
0%Not started
6Polishing and stabilisation
0%Not started

Risks and blockers

✓ No risks or blockers reported this week.

Open questions

Open questionOwnerNeeded by
Customer status: Credit Hold. Acumatica logicIIqra7 Nov
Remove the One-time customer status in AcumaticaIIqra7 Nov
Remove not relevant Nets in AcumaticaNeed Approval10 Nov
Discuss whether there are any Acumatica emailsNeed Approval15 Nov

Change requests

No change requests this week.

SPI = EV / PV · CPI = EV / AC · EAC = BAC / CPI. A value below 1 for SPI or CPI means behind schedule or over budget. BAC (659 h) is derived from the reported EAC and CPI.