Weekly progress report · Earned Value Analysis
| Milestone | Progress | Status | |
|---|---|---|---|
1Foundation and Acumatica connectivity | 100% | Complete | |
2Customers | 45% | In progress | |
3Invoices | 20% | In progress | |
4Payments | 0% | Not started | |
5Refunds | 0% | Not started | |
6Polishing and stabilisation | 0% | Not started |
| Open question | Owner | Needed by |
|---|---|---|
| Customer status: Credit Hold. Acumatica logic | IIqra | 7 Nov |
| Remove the One-time customer status in Acumatica | IIqra | 7 Nov |
| Remove not relevant Nets in Acumatica | Need Approval | 10 Nov |
| Discuss whether there are any Acumatica emails | Need Approval | 15 Nov |
SPI = EV / PV · CPI = EV / AC · EAC = BAC / CPI. A value below 1 for SPI or CPI means behind schedule or over budget. BAC (659 h) is derived from the reported EAC and CPI.